Principles of Mining - LightNovelsOnl.com
You're reading novel online at LightNovelsOnl.com. Please use the follow button to get notifications about your favorite novels and its latest chapters so you can come back anytime and won't miss anything.
FILLING WITH BROKEN ORE SUBSEQUENTLY WITHDRAWN.--This order of support is called by various names, the favorite being "shrinkage-stoping."
The method is to break the ore on to the roof of the level, and by thus filling the stope with broken ore, provide temporary support to the walls and furnish standing floor upon which to work in making the next cut (Figs. 37, 38, and 39.) As broken material occupies 30 to 40% more s.p.a.ce than rock _in situ_, in order to provide working s.p.a.ce at the face, the broken ore must be drawn from along the level after each cut. When the area attacked is completely broken through from level to level, the stope will be full of loose broken ore, which is then entirely drawn off.
A block to be attacked by this method requires preliminary winzes only at the extremities of the stope,--for entry and for ventilation.
Where it is desired to maintain the winzes after stoping, they must either be strongly timbered and lagged on the stope side, be driven in the walls, or be protected by a pillar of ore (Fig.
37). The settling ore and the crus.h.i.+ng after the stope is empty make it difficult to maintain timbered winzes.
[Ill.u.s.tration: Fig. 37.--Longitudinal section of stope filled with broken ore.]
Where it can be done without danger to the mine, the empty stopes are allowed to cave. If such crus.h.i.+ng would be dangerous, either the walls must be held up by pillars of unbroken ore, as in the Alaska Treadwell, where large "rib" pillars are left, or the open s.p.a.ces must be filled with waste. Filling the empty stope is usually done by opening frequent pa.s.ses along the base of the filled stope above, and allowing the material of the upper stope to flood the lower one. This program continued upwards through the mine allows the whole filling of the mine to descend gradually and thus requires replenishment only into the top. The old stopes in the less critical and usually exhausted territory nearer the surface are sometimes left without replenis.h.i.+ng their filling.
The weight of broken ore standing at such a high angle as to settle rapidly is very considerable upon the level; moreover, at the moment when the stope is entirely drawn off, the pressure of the walls as well is likely to be very great. The roadways in this system therefore require more than usual protection. Three methods are used: (_a_) timbering; (_b_) driving a sublevel in the ore above the main roadway as a stoping-base, thus leaving a pillar of ore over the roadway (Fig. 39); (_c_) by dry-walling the levels, as in the Baltic mine, Michigan (Figs. 34 and 35). By the use of sublevels the main roadways are sometimes driven in the walls (Fig. 38) and in many cases all timbering is saved. To recover pillars left below sublevels is a rather difficult task, especially if the old stope above is caved or filled. The use of pillars in subst.i.tution for timber, if the pillars are to be lost, is simply a matter of economics as to whether the lost ore would repay the cost of other devices.
[Ill.u.s.tration: Fig. 38.--Cross-section of "shrinkage" stope.]
Frequent ore-chutes through the level timbers, or from the sublevels, are necessary to prevent lodgment of broken ore between such pa.s.ses, because it is usually too dangerous for men to enter the emptying stope to shovel out the lodged remnants. Where the ore-body is wide, and in order that there may be no lodgment of ore, the timbers over the level are set so as to form a trough along the level; or where pillars are left, they are made "A"-shaped between the chutes, as indicated in Figure 37.
[Ill.u.s.tration: Fig. 39.--Cross-section of "shrinkage" stope.]
The method of breaking the ore in conjunction with this means of support in comparatively narrow deposits can be on the rill, in order to have the advantage of down holes. Usually, however, flat-back or horizontal cuts are desirable, as in such an arrangement it is less troublesome to regulate the drawing of the ore so as to provide proper head room. Where stopes are wide, ore is sometimes cut arch-shaped from wall to wall to a.s.sure its standing. Where this method of support is not of avail, short, sharply tapering stulls are put in from the broken ore to the face (Fig. 39). When the cut above these stulls is taken out, they are pulled up and are used again.
This method of stoping is only applicable when:--
1. The deposit dips over 60, and thus broken material will freely settle downward to be drawn off from the bottom.
2. The ore is consistently payable in character. No selection can be done in breaking, as all material broken must be drawn off together.
3. The hanging wall is strong, and will not crush or spall off waste into the ore.
4. The ore-body is regular in size, else loose ore will lodge on the foot wall. Stopes opened in this manner when partially empty are too dangerous for men to enter for shoveling out remnants.
The advantages of this system over others, where it is applicable, are:--
(_a_) A greater distance between levels can be operated and few winzes and rises are necessary, thus a great saving of development work can be effected. A stope 800 to 1000 feet long can be operated with a winze at either end and with levels 200 or 220 feet apart.
(_b_) There is no shoveling in the stopes at all.
(_c_) No timber is required. As compared with timbering by stulling, it will apply to stopes too wide and walls too heavy for this method.
Moreover, little staging is required for working the face, since ore can be drawn from below in such a manner as to allow just the right head room.
(_d_) Compared to the system of filling with waste, coincidentally with breaking (second method), it saves altogether in some cases the cost of filling. In any event, it saves the cost of ore-pa.s.ses, of shoveling into them, and of the detailed distribution of the filling.
Compared with other methods, the system has the following disadvantages, that:
_A_. The ore requires to be broken in the stopes to a degree of fineness which will prevent blocking of the chutes at the level.
When pieces too large reach the chutes, nothing will open them but blasting,--to the damage of timbers and chutes. Some large rocks are always liable to be buried in the course of ore-breaking.
_B_. Practically no such perfection of walls exists, but some spalling of waste into the ore will take place. A crus.h.i.+ng of the walls would soon mean the loss of large amounts of ore.
_C_. There is no possibility of regulating the mixture of grade of ore by varying the working points. It is months after the ore is broken before it can reach the levels.
_D_. The breaking of 60% more ore than immediate treatment demands results in the investment of a considerable sum of money. An equilibrium is ultimately established in a mine worked on this system when a certain number of stopes full of completely broken ore are available for entire withdrawal, and there is no further acc.u.mulation. But, in any event, a considerable amount of broken ore must be held in reserve. In one mine worked on this plan, with which the writer has had experience, the annual production is about 250,000 tons and the broken ore represents an investment which, at 5%, means an annual loss of interest amounting to 7 cents per ton of ore treated.
_E_. A mine once started on the system is most difficult to alter, owing to the lack of frequent winzes or pa.s.ses. Especially is this so if the only alternative is filling, for an alteration to the system of filling coincident with breaking finds the mine short of filling winzes. As the conditions of walls and ore often alter with depth, change of system may be necessary and the situation may become very embarra.s.sing.
_F_. The restoping of the walls for lower-grade ore at a later period is impossible, for the walls of the stope will be crushed, or, if filled with waste, will usually crush when it is drawn off to send to a lower stope.
The system has much to recommend it where conditions are favorable.
Like all other alternative methods of mining, it requires the most careful study in the light of the special conditions involved. In many mines it can be used for some stopes where not adaptable generally.
It often solves the problem of blind ore-bodies, for they can by this means be frequently worked with an opening underneath only.
Thus the cost of driving a roadway overhead is avoided, which would be required if timber or coincident filling were the alternatives.
In such cases ventilation can be managed without an opening above, by so directing the current of air that it will rise through a winze from the level below, flow along the stope and into the level again at the further end of the stope through another winze.
[Ill.u.s.tration: Fig. 40.--Longitudinal section. Ore-pillar support in narrow stopes.]
SUPPORT BY PILLARS OF ORE.--As a method of mining metals of the sort under discussion, the use of ore-pillars except in conjunction with some other means of support has no general application. To use them without a.s.sistance implies walls sufficiently strong to hold between pillars; to leave them permanently anywhere implies that the ore abandoned would not repay the labor and the material of a subst.i.tute. There are cases of large, very low-grade mines where to abandon one-half the ore as pillars is more profitable than total extraction, but the margin of payability in such ore must be very, very narrow. Unpayable spots are always left as pillars, for obvious reasons. Permanent ore-pillars as an adjunct to other methods of support are in use. Such are the rib-pillars in the Alaska Treadwell, the form of which is indicated by the upward extension of the pillars adjacent to the winzes, shown in Figure 37. Always a careful balance must be cast as to the value of the ore left, and as to the cost of a subst.i.tute, because every ore-pillar can be removed at some outlay. Temporary pillars are not unusual, particularly to protect roadways and shafts. They are, when left for these purposes, removed ultimately, usually by beginning at the farther end and working back to the final exit.
[Ill.u.s.tration: Fig. 41.--Horizontal plan at levels of Broken Hill.
Method of alternate stopes and ore-pillars.]
[Ill.u.s.tration: Fig. 42.--Longitudinal section of Figure 41.]
A form of temporary ore-pillars in very wide deposits is made use of in conjunction with both filling and timbering (Figs. 37, 39, 40). In the use of temporary pillars for ore-bodies 100 to 250 feet wide at Broken Hill, stopes are carried up at right angles to the strike, each fifty feet wide and clear across the ore-body (Figs. 41 and 42). A solid pillar of the same width is left in the first instance between adjacent stopes, and the initial series of stopes are walled with one square-set on the sides as the stope is broken upward. The room between these two lines of sets is filled with waste alternating with ore-breaking in the usual filling method.
When the ore from the first group of alternate stopes (_ABC_, Fig.
42) is completely removed, the pillars are stoped out and replaced with waste. The square-sets of the first set of stopes thus become the boundaries of the second set. Entry and ventilation are obtained through these lines of square-sets, and the ore is pa.s.sed out of the stopes through them.
[Ill.u.s.tration: Fig. 43.--Cross-section of stull support with waste reenforcement.]
ARTIFICIAL PILLARS.--This system also implies a roof so strong as not to demand continuous support. Artificial pillars are built in many different ways. The method most current in fairly narrow deposits is to reenforce stulls by packing waste above them (Figs.
43 and 44). Not only is it thus possible to economize in stulls by using the waste which acc.u.mulates underground, but the principle applies also to cases where the stulls alone are not sufficient support, and yet where complete filling or square-setting is unnecessary. When the conditions are propitious for this method, it has the comparative advantage over timber systems of saving timber, and over filling systems of saving imported filling. Moreover, these constructions being pillar-shaped (Fig. 44), the intervals between them provide outlets for broken ore, and specially built pa.s.ses are unnecessary. The method has two disadvantages as against the square-set or filling process, in that more staging must be provided from which to work, and in stopes over six feet the erection of machine-drill columns is tedious and costly in time and wages.
[Ill.u.s.tration: Fig. 44.--Longitudinal section of stull and waste pillars.]
In wide deposits of markedly flat, irregular ore-bodies, where a definite system is difficult and where timber is expensive, cribs of cord-wood or logs filled with waste after the order shown in Figure 31, often make fairly sound pillars. They will not last indefinitely and are best adapted to the temporary support of the ore-roof pending filling. The increased difficulty in setting up machine drills in such stopes adds to the breaking costs,--often enough to warrant another method of support.
[Ill.u.s.tration: Fig. 45.--Sublevel caving system.]
CAVING SYSTEMS.--This method, with variations, has been applied to large iron deposits, to the Kimberley diamond mines, to some copper mines, but in general it has little application to the metal mines under consideration, as few ore-bodies are of sufficiently large horizontal area. The system is dependent upon a large area of loose or "heavy" ground pressing directly on the ore with weight, such that if the ore be cut into pillars, these will crush. The details of the system vary, but in general the _modus operandi_ is to prepare roadways through the ore, and from the roadways to put rises, from which sublevels are driven close under the floating ma.s.s of waste and ore,--sometimes called the "matte" (Fig. 45).
The pillars between these sublevels are then cut away until the weight above crushes them down. When all the crushed ore which can be safely reached is extracted, retreat is made and another series of subopenings is then driven close under the "matte." The pillar is reduced until it crushes and the operation is repeated.
Eventually the bottom strata of the "matte" become largely ore, and a sort of equilibrium is reached when there is not much loss in this direction. "Top slicing" is a variation of the above method by carrying a horizontal stope from the rises immediately under the matte, supporting the floating material with timber. At Kimberley the system is varied in that galleries are run out to the edge of the diamond-iferous area and enlarged until the pillar between crushes.
In the caving methods, between 40 and 50% of the ore is removed by the preliminary openings, and as they are all headings of some sort, the average cost per ton of this particular ore is higher than by ordinary stoping methods. On the other hand, the remaining 50 to 60% of the ore costs nothing to break, and the average cost is often remarkably low. As said, the system implies bodies of large horizontal area. They must start near enough to the surface that the whole superinc.u.mbent ma.s.s may cave and give crus.h.i.+ng weight, or the immediately overhanging roof must easily cave. All of these are conditions not often met with in mines of the character under review.
CHAPTER XII.
Mechanical Equipment.